Water flow procedure with "water drain operation plug" in the room

Q

Water flow procedure with "water drain operation plug" in the room

A

There may be an operating tap for drainage in the room.

※ Drainage is mainly installed in the toilet and around the washing machine storage area.


● Water flow procedure

①Make sure that all water taps, such as the kitchen and bathroom (washout), are closed.

(If the faucet is open, please close it once.)


②Turn the drain valve handle at each location in the direction of "flow「通水」"


"Water flow procedure" is completed . Open the faucet and check that the water comes out.

※ Please note that water will come out vigorously when water is drained first after water flow.

(Please turn the faucet little by little.)